Question
The figure shows a tank made up of 3 sections. Cuboid J with a square base of side 9 cm and height 32 cm. Cube K with a side of 17 cm. Cuboid L that is 62 cm by 19 cm by 40 cm. Water from a tap above flows down at a rate of 3.1 litres per minute while water is drained out from the bottom at a rate of 1 litre per minute. How long did it take to fill up the tank to a height of 65 cm from the base? Give the answer in minutes correct to nearest whole number.
3 m

Click button first when a symbol is required. X

The figure shows a tank made up of 3 sections. Cuboid J with a square base of side 9 cm and height 32 cm. Cube K with a side of 17 cm. Cuboid L that is 62 cm by 19 cm by 40 cm. Water from a tap above flows down at a rate of 3.1 litres per minute while water is drained out from the bottom at a rate of 1 litre per minute. How long did it take to fill up the tank to a height of 65 cm from the base? Give the answer in minutes correct to nearest whole number.