Question
If Peter and Reggie work together, they can complete a job in 12 days. If Peter and Reggie worked together for 8 days, followed by Reggie who worked alone for the next 20 days, they can finish off the job.
  1. How many days would Reggie need to complete the job alone? 
  2. How many days would Peter need to complete the job alone?