Question
If Brandon and Owen work together, they can complete a job in 12 days. If Brandon and Owen worked together for 6 days, followed by Owen who worked alone for the next 24 days, they can finish off the job.
  1. How many days would Owen need to complete the job alone? 
  2. How many days would Brandon need to complete the job alone?