Question
If Nora and Lilian work together on a project, they will complete it in 5 days. If Lilian were to work with Gabriel on the same project, they will take a day longer. If Gabriel and Salik work together, they will take 120% more time than Nora and Lilian. If Nora and Salik were to work together, how many more days will they take to complete the project compared to Lilian and Gabriel working together?
4 m

Click button first when a symbol is required. X

If Nora and Lilian work together on a project, they will complete it in 5 days. If Lilian were to work with Gabriel on the same project, they will take a day longer. If Gabriel and Salik work together, they will take 120% more time than Nora and Lilian. If Nora and Salik were to work together, how many more days will they take to complete the project compared to Lilian and Gabriel working together?