If Leah and Elijah work together on a project, they will complete it in 10 days. If Elijah were to work with Josiah on the same project, they will take a day longer. If Josiah and Gabriel work together, they will take 150% more time than Leah and Elijah. If Leah and Gabriel were to work together, how many more days will they take to complete the project compared to Elijah and Josiah working together?
4 m

Click button first when a symbol is required. X

If Leah and Elijah work together on a project, they will complete it in 10 days. If Elijah were to work with Josiah on the same project, they will take a day longer. If Josiah and Gabriel work together, they will take 150% more time than Leah and Elijah. If Leah and Gabriel were to work together, how many more days will they take to complete the project compared to Elijah and Josiah working together?