If Owen and Zoe work together on a project, they will complete it in 10 days. If Zoe were to work with Joshua on the same project, they will take a day longer. If Joshua and Bryan work together, they will take 60% more time than Owen and Zoe. If Owen and Bryan were to work together, how many more days will they take to complete the project compared to Zoe and Joshua working together?
4 m

Click button first when a symbol is required. X

If Owen and Zoe work together on a project, they will complete it in 10 days. If Zoe were to work with Joshua on the same project, they will take a day longer. If Joshua and Bryan work together, they will take 60% more time than Owen and Zoe. If Owen and Bryan were to work together, how many more days will they take to complete the project compared to Zoe and Joshua working together?