Question
If Joseph and Leah work together on a project, they will complete it in 12 days. If Leah were to work with Claire on the same project, they will take a day longer. If Claire and Rebecca work together, they will take 150% more time than Joseph and Leah. If Joseph and Rebecca were to work together, how many more days will they take to complete the project compared to Leah and Claire working together?
4 m

Click button first when a symbol is required. X

If Joseph and Leah work together on a project, they will complete it in 12 days. If Leah were to work with Claire on the same project, they will take a day longer. If Claire and Rebecca work together, they will take 150% more time than Joseph and Leah. If Joseph and Rebecca were to work together, how many more days will they take to complete the project compared to Leah and Claire working together?