Question
If Raeann and Liam work together on a project, they will complete it in 10 days. If Liam were to work with Leah on the same project, they will take a day longer. If Leah and Jack work together, they will take 110% more time than Raeann and Liam. If Raeann and Jack were to work together, how many more days will they take to complete the project compared to Liam and Leah working together?
4 m

Click button first when a symbol is required. X

If Raeann and Liam work together on a project, they will complete it in 10 days. If Liam were to work with Leah on the same project, they will take a day longer. If Leah and Jack work together, they will take 110% more time than Raeann and Liam. If Raeann and Jack were to work together, how many more days will they take to complete the project compared to Liam and Leah working together?