Question
If Leah and Oliver work together on a project, they will complete it in 12 days. If Oliver were to work with Elijah on the same project, they will take a day longer. If Elijah and Ethan work together, they will take 50% more time than Leah and Oliver. If Leah and Ethan were to work together, how many more days will they take to complete the project compared to Oliver and Elijah working together?
4 m

Click button first when a symbol is required. X

If Leah and Oliver work together on a project, they will complete it in 12 days. If Oliver were to work with Elijah on the same project, they will take a day longer. If Elijah and Ethan work together, they will take 50% more time than Leah and Oliver. If Leah and Ethan were to work together, how many more days will they take to complete the project compared to Oliver and Elijah working together?