If Victoria and Leah work together on a project, they will complete it in 8 days. If Leah were to work with Henry on the same project, they will take a day longer. If Henry and Bryan work together, they will take 100% more time than Victoria and Leah. If Victoria and Bryan were to work together, how many more days will they take to complete the project compared to Leah and Henry working together?
4 m

Click button first when a symbol is required. X

If Victoria and Leah work together on a project, they will complete it in 8 days. If Leah were to work with Henry on the same project, they will take a day longer. If Henry and Bryan work together, they will take 100% more time than Victoria and Leah. If Victoria and Bryan were to work together, how many more days will they take to complete the project compared to Leah and Henry working together?