Question
If Jacob and Christopher work together on a project, they will complete it in 12 days. If Christopher were to work with Evan on the same project, they will take a day longer. If Evan and Hannah work together, they will take 50% more time than Jacob and Christopher. If Jacob and Hannah were to work together, how many more days will they take to complete the project compared to Christopher and Evan working together?
4 m

Click button first when a symbol is required. X

If Jacob and Christopher work together on a project, they will complete it in 12 days. If Christopher were to work with Evan on the same project, they will take a day longer. If Evan and Hannah work together, they will take 50% more time than Jacob and Christopher. If Jacob and Hannah were to work together, how many more days will they take to complete the project compared to Christopher and Evan working together?