Question
If Ethan and Leah work together on a project, they will complete it in 6 days. If Leah were to work with Noah on the same project, they will take a day longer. If Noah and Olivia work together, they will take 50% more time than Ethan and Leah. If Ethan and Olivia were to work together, how many more days will they take to complete the project compared to Leah and Noah working together?
4 m

Click button first when a symbol is required. X

If Ethan and Leah work together on a project, they will complete it in 6 days. If Leah were to work with Noah on the same project, they will take a day longer. If Noah and Olivia work together, they will take 50% more time than Ethan and Leah. If Ethan and Olivia were to work together, how many more days will they take to complete the project compared to Leah and Noah working together?