Question
If Hannah and Salik work together on a project, they will complete it in 5 days. If Salik were to work with Andrew on the same project, they will take a day longer. If Andrew and Harris work together, they will take 140% more time than Hannah and Salik. If Hannah and Harris were to work together, how many more days will they take to complete the project compared to Salik and Andrew working together?
4 m

Click button first when a symbol is required. X

If Hannah and Salik work together on a project, they will complete it in 5 days. If Salik were to work with Andrew on the same project, they will take a day longer. If Andrew and Harris work together, they will take 140% more time than Hannah and Salik. If Hannah and Harris were to work together, how many more days will they take to complete the project compared to Salik and Andrew working together?