If Ryan and Maya work together on a project, they will complete it in 10 days. If Maya were to work with Jack on the same project, they will take a day longer. If Jack and Jamie work together, they will take 90% more time than Ryan and Maya. If Ryan and Jamie were to work together, how many more days will they take to complete the project compared to Maya and Jack working together?
4 m

Click button first when a symbol is required. X

If Ryan and Maya work together on a project, they will complete it in 10 days. If Maya were to work with Jack on the same project, they will take a day longer. If Jack and Jamie work together, they will take 90% more time than Ryan and Maya. If Ryan and Jamie were to work together, how many more days will they take to complete the project compared to Maya and Jack working together?