Question
If Audrey and Owen work together on a project, they will complete it in 10 days. If Owen were to work with Samantha on the same project, they will take a day longer. If Samantha and Lilian work together, they will take 200% more time than Audrey and Owen. If Audrey and Lilian were to work together, how many more days will they take to complete the project compared to Owen and Samantha working together?
4 m

Click button first when a symbol is required. X

If Audrey and Owen work together on a project, they will complete it in 10 days. If Owen were to work with Samantha on the same project, they will take a day longer. If Samantha and Lilian work together, they will take 200% more time than Audrey and Owen. If Audrey and Lilian were to work together, how many more days will they take to complete the project compared to Owen and Samantha working together?