Question
If Wyatt and Levi work together on a project, they will complete it in 11 days. If Levi were to work with Anna on the same project, they will take a day longer. If Anna and Salik work together, they will take 200% more time than Wyatt and Levi. If Wyatt and Salik were to work together, how many more days will they take to complete the project compared to Levi and Anna working together?
4 m

Click button first when a symbol is required. X

If Wyatt and Levi work together on a project, they will complete it in 11 days. If Levi were to work with Anna on the same project, they will take a day longer. If Anna and Salik work together, they will take 200% more time than Wyatt and Levi. If Wyatt and Salik were to work together, how many more days will they take to complete the project compared to Levi and Anna working together?