Question
If Hazel and Olivia work together on a project, they will complete it in 10 days. If Olivia were to work with Violet on the same project, they will take a day longer. If Violet and Christian work together, they will take 160% more time than Hazel and Olivia. If Hazel and Christian were to work together, how many more days will they take to complete the project compared to Olivia and Violet working together?
4 m

Click button first when a symbol is required. X

If Hazel and Olivia work together on a project, they will complete it in 10 days. If Olivia were to work with Violet on the same project, they will take a day longer. If Violet and Christian work together, they will take 160% more time than Hazel and Olivia. If Hazel and Christian were to work together, how many more days will they take to complete the project compared to Olivia and Violet working together?