Question
If Levi and Roshel work together on a project, they will complete it in 12 days. If Roshel were to work with Victoria on the same project, they will take a day longer. If Victoria and Bryan work together, they will take 200% more time than Levi and Roshel. If Levi and Bryan were to work together, how many more days will they take to complete the project compared to Roshel and Victoria working together?
4 m

Click button first when a symbol is required. X

If Levi and Roshel work together on a project, they will complete it in 12 days. If Roshel were to work with Victoria on the same project, they will take a day longer. If Victoria and Bryan work together, they will take 200% more time than Levi and Roshel. If Levi and Bryan were to work together, how many more days will they take to complete the project compared to Roshel and Victoria working together?