Question
If John and Michael work together on a project, they will complete it in 9 days. If Michael were to work with Julie on the same project, they will take a day longer. If Julie and Charlotte work together, they will take 200% more time than John and Michael. If John and Charlotte were to work together, how many more days will they take to complete the project compared to Michael and Julie working together?
4 m

Click button first when a symbol is required. X

If John and Michael work together on a project, they will complete it in 9 days. If Michael were to work with Julie on the same project, they will take a day longer. If Julie and Charlotte work together, they will take 200% more time than John and Michael. If John and Charlotte were to work together, how many more days will they take to complete the project compared to Michael and Julie working together?