Question
If Roshel and David work together on a project, they will complete it in 5 days. If David were to work with Jeremiah on the same project, they will take a day longer. If Jeremiah and Rachel work together, they will take 60% more time than Roshel and David. If Roshel and Rachel were to work together, how many more days will they take to complete the project compared to David and Jeremiah working together?
4 m

Click button first when a symbol is required. X

If Roshel and David work together on a project, they will complete it in 5 days. If David were to work with Jeremiah on the same project, they will take a day longer. If Jeremiah and Rachel work together, they will take 60% more time than Roshel and David. If Roshel and Rachel were to work together, how many more days will they take to complete the project compared to David and Jeremiah working together?