If Evan and Anthony work together on a project, they will complete it in 10 days. If Anthony were to work with Rebecca on the same project, they will take a day longer. If Rebecca and Nathan work together, they will take 120% more time than Evan and Anthony. If Evan and Nathan were to work together, how many more days will they take to complete the project compared to Anthony and Rebecca working together?
4 m
If Evan and Anthony work together on a project, they will complete it in 10 days. If Anthony were to work with Rebecca on the same project, they will take a day longer. If Rebecca and Nathan work together, they will take 120% more time than Evan and Anthony. If Evan and Nathan were to work together, how many more days will they take to complete the project compared to Anthony and Rebecca working together?
Symbols
Enter the numerator and denominator
Enter value
2
1-minute grace period
When you click the Next button, you will be given 1-minute grace period to decide
whether to do the next question type.
The question will be marked as incorrect if you exceed 1 minute and leave the question page.
Click the Back button instead if you would like to return to the topic page.
Ischool Pte Ltd
Date:03 May 2024
Topic:
SPEED
Question Code:
P6.SP.TL.18012231
Student:
Class:
Level:
School:
If Evan and Anthony work together on a project, they will complete it in 10 days. If Anthony were to work with Rebecca on the same project, they will take a day longer. If Rebecca and Nathan work together, they will take 120% more time than Evan and Anthony. If Evan and Nathan were to work together, how many more days will they take to complete the project compared to Anthony and Rebecca working together?
(4 m)
Ischool Pte Ltd
Date:
03 May 2024
Topic:
SPEED
Question Code:
P6.SP.TL.18012231
Student:
Class:
Level:
School:
If Evan and Anthony work together on a project, they will complete it in 10 days. If Anthony were to work with Rebecca on the same project, they will take a day longer. If Rebecca and Nathan work together, they will take 120% more time than Evan and Anthony. If Evan and Nathan were to work together, how many more days will they take to complete the project compared to Anthony and Rebecca working together?
If Evan and Anthony work together on a project, they will complete it in 10 days. If Anthony were to work with Rebecca on the same project, they will take a day longer. If Rebecca and Nathan work together, they will take 120% more time than Evan and Anthony. If Evan and Nathan were to work together, how many more days will they take to complete the project compared to Anthony and Rebecca working together?
Message
To help you learn well, you can save up to
5 questions per question types in the Notepad History for review.
The latest 5 questions willautomatically replace the earliest one.
If a question islocked, it will not be automatically deleted.
If 5 questions are locked, new questionscannot be saved.
To save new questions,unlock ordelete the existing questions in the
notepad history.
ISchool Pte Ltd
Date:03 May 2024
Topic:SPEED
Question Number:P6.SP.TL.18012231-A1
Student:
Class:
Level:
School:
Promo Code
Promo Code:
SELECT PLAN TYPE
Subscribe Today!
Oops! The free trial period has expired.
Enjoy the full features by subscribing to iSchool today.